Date published
July 27 2026
Road resurfacing and paving are scheduled to take place under the following schedule this summer:
- Concession 6 North Nottawasaga from County Road 91 to 33/34 Sideroad Nottawasaga beginning July 27th, with completion planned for August 25th.
- Concession 10 South from County Road 91 to County Road 124 beginning August 4th with completion planned for August 25th.
The work includes asphalt pulverization and road reshaping followed by new asphalt placement.
During resurfacing, the roads will be closed to through traffic. Access will be provided to businesses operating on the road and to residents who live on the road. Emergency services, school buses, Canada Post, and garbage/recycling will also have access.
For more information, please contact:
Scott Haw
Capital Works Technologist
Clearview Township
(705) 428-6230 ext. 233
shaw@clearview.ca