Notice - County Road 42 Schedule of Watermain Replacement

Date Published: 
December 19 2019

The work related to the replacement of the existing watermain on County Road 42 (Airport Road) from MAS 1882 CR 42 to John Street will be on-going into the spring of 2020.

To date, the Contractor has completed the installation of the proposed watermain and is currently testing the watermain before the new watermain is connected to the existing water system. 

The testing and connection of the watermain is scheduled to be completed by March 2020.  Advance notification will be issued to residents for scheduled water service interruptions.   

The restoration work related to the topsoil, seed/sod and driveways will be completed in May 2020. 

We apologize for any inconvenience. Should you have any questions or require any further information, please do not hesitate to contact the undersigned. Thank you for your cooperation and patience during this construction period.

Thank You,

Todd Patton
Public Works Manager
Township of Clearview
www.clearview.ca
P. 705-428-5024
F. 705-428-2993

Lyle Simpson,
Intermediate Inspector
R.J. Burnside & Associates Limited
lyle.simpson@rjburnside.com
Office: 705-446-0515
Direct Line: 705-797-4306